PHILLIPSBURG, N.J. — The Delaware River Joint Toll Bridge Commission (DRJTBC) recently awarded contracts for cleaning and painting the twin-span I-78 Toll Bridge in 2027.
The project marks the first time the bridge will be repainted since its opening 37 years ago — on Nov. 21, 1989. A series of other tasks are expected to be performed during the project, including some steel repairs, drainage work, and improvements to approach bridges along the Commission’s I-78 roadway segments in Pennsylvania and New Jersey.
Members of the bistate commission approved contracts for the project at their monthly meeting on Nov. 23 in Lower Makefield, PA. The project’s painting and repairs contract was awarded to Anselmi & DeCicco, Inc. of Maplewood, N.J. for a not-to-exceed amount of $11,655,265. A corresponding construction management/inspections contract was awarded to STV, Inc. of Lawrenceville, N.J. for a not-to-exceed amount of $1,553,970.31.
Specific construction activities will include, but not be limited to, the following tasks:
- Cleaning and painting of the seven-span twin bridge steel superstructures over the Delaware River;
- Steel repairs where warranted;
- Replacement of drain troughs at the river bridge’s abutments;
- Deck and substructure crack and spall repairs at the river bridge and its approach bridges;
- Epoxy waterproof coating of bridge seats throughout the Commission’s I-78 jurisdiction;
- Repairs to deteriorated slopes along the Commission’s I-78 roadway segments;
- Resetting rocker bearings as warranted on the river bridge and its approach bridges; and
- Resealing deck joints on the bridges in the Commission I-78 jurisdiction.
The I-78 Toll Bridge is the Commission’s most heavily traveled river crossing. The bridges and its approaches carried 66,000 vehicles in 2025. The bridge is notable as an interstate connection between North Jersey port facilities and Pennsylvania’s warehouses in the Lehigh Valley and points south, west, and north.
Project planning stems from a series of deficiencies identified in the Commission’s 2025 Annual Maintenance Report and subsequent field inspections conducted by the Engineering and Capital Program Management consultant staff.
Project preparation activities are anticipated to begin in January. Cleaning and painting would then follow, with drainage related tasks taking place later.
A series of lane and shoulder closures will be needed to carry out various aspects of the project. Specific details on travel impacts will be announced as those details become available next year.
If all goes according to plan, the project should reach completion by the end of next year.